You seem to be using an unsupported browser
You can continue browsing, but please use a supported browser to improve your experience.
Got it
Turn on more accessible mode
Turn off more accessible mode
Sign In
e-services
PDO Mail
PDO Staff
Flight Schedule
PDO Self-Service Password Reset
home
careers
contact
It looks like your browser does not have JavaScript enabled. Please turn on JavaScript and try again.
youtube
youtube
linkedin
instagram
facebook
Home
HSE Policy
Corporate HSE Business Plan
Golden Rules
Life Saving Rules
Page Content
2021 2nd Alert HiPo36 Mid identification and cutting the wrong pipeline
As per the normal cold cutting practice, contractor crew who were assigned for re-routing existing flow lines, identified, line walked and marked ‘C” on a flowline at cut points using red paint. They also marked red “C” on adjacent Long Term Closed (LTC) flow line based on the verbal confirmation that it is hydrocarbon free. This was done to save time as this line was scheduled for cut on following day. At the time of cold cut, additional red marking on the LTC line caused confusion resulting erroneous cutting of the wrong sequence line.
Always verify identification of the lines before cold cut. Always seek clarification in case the procedures are not clear. Always follow reliable identification methods like hammering, pigging. Sign off flowline by all concerned – Area Authority, Permit Applicant & Holder. Never take short cuts. Never allow the Permit holder to physically involve in carrying out activities