2020 2nd alert HiPo#01 (Drops) safety valve joint sheared
At approximately 03:50 AM on 19th January 2020, Hoist was in process of pulling the work string after the cutting attempt. The landing joint coupling with Safety Valve snapped off and landed beside the draw-works, damaging the hydraulic valve mounting bolts of the mast raising cylinder. Zone management was followed, and nobody got injured.
Always ensure slip type elevator is used for Vam-top connections. Always ensure the presence of third-party personnel whilst their equipment are in use. Always ensure Third party personnel are attending TBT. Ensure call out specifies the correct type of equipment as per OEM recommendations. Ensure SOP is provided for all outsourced equipment. Ensure zone management is always followed (positive finding in this case).

Category:Second AlertsDocument Type:Safety