You seem to be using an unsupported browser
You can continue browsing, but please use a supported browser to improve your experience.
Got it
Turn on more accessible mode
Turn off more accessible mode
Sign In
e-services
PDO Mail
PDO Staff
Flight Schedule
PDO Self-Service Password Reset
home
careers
contact
It looks like your browser does not have JavaScript enabled. Please turn on JavaScript and try again.
youtube
youtube
linkedin
instagram
facebook
Home
HSE Policy
Corporate HSE Business Plan
Golden Rules
Life Saving Rules
Page Content
2019 Second Alert HiPo#31 Lifting
An electrical crew was engaged in guard pole erection at Hawqa 23 road crossing location. The crane operator raised the pole into the vertical position. While attempting to lift the guard pole, the round endless sling failed to grip the pole and the sling slipped off. The concrete pole toppled onto the crane at the rear side of the driver cabin.
Ensure correct rigging method and proper equipment used for lifting activity
Category:
Safety Alerts
Document Type:
Safety
Format:
.pptx
Viewers:
30
Download:
English