You seem to be using an unsupported browser
You can continue browsing, but please use a supported browser to improve your experience.
Got it
Turn on more accessible mode
Turn off more accessible mode
Sign In
e-services
PDO Mail
PDO Staff
Flight Schedule
PDO Self-Service Password Reset
home
careers
contact
It looks like your browser does not have JavaScript enabled. Please turn on JavaScript and try again.
youtube
youtube
linkedin
instagram
facebook
Home
HSE Policy
Corporate HSE Business Plan
Golden Rules
Life Saving Rules
Page Content
2017 Second Alert - HiPo#1
During offloading the 12” pipe from a trailer with a 25T crane, an auxiliary hook Rope failed. It happened when two pipes were lifted from the trailer to make Space for inserting wooden planks. The auxiliary hook wire rope snapped and the hook fell down missing the nearest banksman.
Always ensure lifting equipment and attachments have a valid 3rd party certification. Always ensure the crane operators conduct a pre-work check. Always ensure compulsory safety checks are conducted when lifting equipment arrives at site. Always ensure you have a lifting plan in place. Ensure staff and supervisors are trained and understand their responsibilities.
Category:
Second Alerts