2017 Second Alert - HiPo#1
During offloading the 12” pipe from a trailer with a 25T crane, an auxiliary hook Rope failed. It happened when two pipes were lifted from the trailer to make Space for inserting wooden planks. The auxiliary hook wire rope snapped and the hook fell down missing the nearest banksman.
Always ensure lifting equipment and attachments have a valid 3rd party certification. Always ensure the crane operators conduct a pre-work check. Always ensure compulsory safety checks are conducted when lifting equipment arrives at site. Always ensure you have a lifting plan in place. Ensure staff and supervisors are trained and understand their responsibilities.