You seem to be using an unsupported browser
You can continue browsing, but please use a supported browser to improve your experience.
Got it
Turn on more accessible mode
Turn off more accessible mode
Sign In
e-services
PDO Mail
PDO Staff
Flight Schedule
PDO Self-Service Password Reset
home
careers
contact
It looks like your browser does not have JavaScript enabled. Please turn on JavaScript and try again.
youtube
youtube
linkedin
instagram
facebook
Home
HSE Policy
Corporate HSE Business Plan
Golden Rules
Life Saving Rules
Page Content
2021 2nd Alert HiPo#14A 12 tones Generator fell during crane lifting
A hired crane was being used to lift a generator from a temporary barricaded area onto a low-bed. After the load was slung, the operator began lifting the load which was beyond the load bearing capacity, the weight proved to be too heavy for the crane to sustain , causing the crane cabin to get dislodged from its position. The boom along with the generator dropped to the ground causing damage to the crane and the generator. No personnel involved in the activity were injured
Ensure the implementation of lift plan, TRIC and risk assessment for all lifting activities. Conduct TBT and discuss the 10 questions for safe lift to all personnel involved in the task. Ensure Lifting supervisor is supervising the lifting operation. STOP Lifting operation on finding any unsafe condition or act.
Category:
Second Alerts
Document Type:
Safety