Sign In
2020 2nd alert HiPo#13 (OHL) Excavation next to LV flowline
Mechanical excavation using a JCB backhoe for road crossing executed very close to the live flowline without keeping a safe distance of 1 meter from the live flowline.
Always ensure that you maintain the 1 meter safe distance from live line for mechanical excavation or 0.5 meter to be maintained after ensuing the live line is isolated. Always ensure that you identify the Buried line and mark the entire session. Always make sure that you do the trial pit before mechanical excavation. Always ensure compliance to PTW system as per PR-1172 requirement.

Category:Second AlertsDocument Type:Safety
Format:.pptxViewers:42
Download: