You seem to be using an unsupported browser
You can continue browsing, but please use a supported browser to improve your experience.
Got it
Turn on more accessible mode
Turn off more accessible mode
Sign In
e-services
PDO Mail
PDO Staff
Flight Schedule
PDO Self-Service Password Reset
home
careers
contact
It looks like your browser does not have JavaScript enabled. Please turn on JavaScript and try again.
youtube
youtube
linkedin
instagram
facebook
Home
HSE Policy
Corporate HSE Business Plan
Golden Rules
Life Saving Rules
Page Content
2019 PS Alert HiPo Gas leak through SOV
A well was expected to produce with a GOR of 100 m3/m3 but the actual GOR turned out to be 5x higher. As a result, when started up and lined up to the station its production resulted in slugging operation. To prevent slugging a Well Test Unit was hooked up at the well site. As a result, pressure was also building up in the A-annulus and was exceeding the MAASP. The pressure from the A-annulus was bled off to the Well Test Unit using the outer Side Outlet Valve. This was done several times and led to the washing out of the valve body resulting in a leak. That leak occurred 3 days after the Well Test Unit was put into operation. By closing the inner SOV the leak was arrested and the well remained in operation via the tubing and the Well Test Unit to the station for several days before the leaking valve was replaced.
SOV shall not be used as a choke as per PR-1489 (Well Test Procedure) and SP-1213 (Well Control), instead a properly designed choke manifold shall be used.