You seem to be using an unsupported browser
You can continue browsing, but please use a supported browser to improve your experience.
Got it
Turn on more accessible mode
Turn off more accessible mode
Sign In
e-services
PDO Mail
PDO Staff
Flight Schedule
PDO Self-Service Password Reset
home
careers
contact
It looks like your browser does not have JavaScript enabled. Please turn on JavaScript and try again.
youtube
youtube
linkedin
instagram
facebook
Home
HSE Policy
Corporate HSE Business Plan
Golden Rules
Life Saving Rules
Page Content
2019 Second Alert HiPo#31 Dropped guard pole during lifting
ATE Sub contractor electrical crew was engaged in guard pole erection at Hawqa 23 road crossing location. The crane operator raised the pole into the vertical position. While attempting to lift the guard pole, the round endless sling failed to grip the pole and the sling slipped off. The concrete pole toppled onto the crane at the rear side of the driver cabin
Always ensure approved lifting plan is available before commencement of lifting activity. Always ensure that correct rigging method is used for lifting. Always ensure right equipment are in place before commencement of task.. Always ensure proper communication and coordination between AP, PA and crew members. Ensure correct rigging method and proper equipment used for lifting activity