2016 Second Alert - LTI Rig 97
A team were attempting to remove the choke line hose (CLH) from the BOP with the help of a forklift truck. When they found the CLH was stuck, the Night Tool Pusher instructed the floor man to collect a pry bar. While the team were waiting for the pry bar, the derrick man tried to release the CLH, using a sledge hammer. Whilst hitting the flange with the hammer, the CLH became free dropping on his left foot.
Use the correct securing method for the task. Ensure the correct equipment is used for the task. Ensure you stay out of the line of fire. Always keep a safe distance from the load with a potential to drop.
Stay out of the line of fire